The TMC project will be completed in phases over a number of years. Below are key milestones along the way.
Spring/Summer 2006
Relocation of great crested newts to new habitat areas to ensure they are protected.
Summer/Autumn/Winter 2006
Reclamation and infrastructure works commence to prepare the site for construction
Summer/Autumn 2006
Parkside Community Centre vacated and demolished (temporary accommodation to be provided in the Ketley Infants School building)
Autumn 2006 - Spring 2007
Enhancements to playing fields carried out, including laying new drainage and capping mine
January 2007
Construction of Phase 1 housing commences - this will be in the south - western part of the site
Summer/Autumn 2007
First phase of housing complete
Winter 2007
Reclamation and infrastructure works complete
Winter/Spring 2008
New community centre complete
Autumn/Winter 2008
New school complete
|